Success Story 3
M.R.Organisation Limited - Compressor Warriors in Action!
Another challenge met; another customer satisfied! A client needed to revive their shut-down plant in just 30 days, requiring various components and a complete oil free compressor overhaul. ⏱
M.R.Organisation Limited rose to the occasion! Within 10 days of receiving the PO, we delivered the necessary materials - 3 HP & 2 LP elements, C maintenance kits, and 100+ other components. On day 11, our 6-person team hit the ground running at the plant.
Within a week, all compressors were operational, and the plant restarted well ahead of schedule! This is what sets M.R.Organisation Limited - unmatched speed, service, and customer satisfaction.
A huge thank you to our incredible team! You're the true warriors, tackling even the toughest jobs with ease.
We live and breathe compressors - they're in our blood!
Bhavesh Patel - VP - Technical Services